THE Taguig City Regional Trial Court (RTC) that issued a temporary restraining order (TRO) against two Manila Electric Co. (Meralco) biddings for 1,000 MW of additional electric supply has extended the TRO duration from 72 hours to 20 days.
The TRO was in response to the petition of the operators of the Malampaya gas project against the Meralco bidding, which was to be done through the Competitive Selection Process (CSP) on August 2 and August 9.